Limestone Middle School is currently scheduled to be open for business on August 20 for the first day of school. However, the new addition will not be completed by that date.

The components of the reconstruction are the site work, inside remodeling on north and south buildings, and new construction. 

According to Rich Decman, superintendent, “As long as the site work and remodeling are finished in the current north and south buildings, we can start school. I am being told that all of that is on time as of right now.” 

The new construction, however, will not be finished until at least the end of August.

Finishing the new section of LMS is not vital to its opening on time. Decman continues, “School can and will proceed without that being completed, almost as it was last year during construction.”